Al Dur IWPP Phase II – Heavy and Oversized Cargo Logistics.
Al Sharif provided integrated heavy-lift logistics services for SEPCOIII Electric Power Construction Co., Ltd. in connection with the Al Dur Independent Water and Power Project (IWPP) Phase II.

From 2019 to 2022, the project involved the intermediate handling, marine transportation and final site delivery of more than 100,000 metric tonnes of heavy and oversized cargo. The operation required coordinated port handling, barging, roll-on/roll-off activities and specialised road transportation.
Al Dur IWPP Phase II – Heavy and Oversized Cargo Logistics
Project Information
ClientSEPCOIII Electric Power Construction Co., Ltd.
ProjectAl Dur Independent Water and Power Project – Phase II
LocationBahrain
Project Period2019–2022
Cargo VolumeMore than 100,000 MT
Cargo TypeHeavy-lift and oversized project cargo
ServicesPort handling, barging, roll-on/roll-off operations and transportation to site

Project Scope

- Receipt and inspection of heavy and oversized cargo at the port
- Intermediate handling and temporary storage
- Verification of cargo dimensions, weights and transport requirements
- Preparation of lifting, loading and transportation plans
- Arrangement of suitable barges and marine equipment
- Roll-on and roll-off operations at the port and landing location
- Marine transportation of project cargo
- Deployment of modular trailers and heavy-duty prime movers
- Transportation from the discharge point to the project site
- Coordination with the client, port authorities, marine teams and site personnel
- Compliance with project safety and operational requirements

Our Solution

Al Sharif developed an integrated port-to-site logistics solution for the movement of heavy and oversized equipment required for the Al Dur IWPP Phase II project.

Cargo was received and handled at the port using suitable heavy-lift equipment before being positioned on specialised modular trailers. Where direct road transportation was restricted or operationally unsuitable, the loaded trailers were moved onto barges through controlled roll-on operations.

The cargo was transported by sea to the designated landing location, rolled off the barge and subsequently transported to the project site using multi-axle trailers and heavy-duty prime movers.

Detailed engineering studies, route surveys, load-distribution calculations, marine planning and cargo-securing procedures were implemented for each movement. Dedicated project teams coordinated the port, marine and land-transport activities to maintain safe and efficient operations throughout the project period.

Project Result

Al Sharif successfully handled and transported more than 100,000 metric tonnes of heavy and oversized cargo for the Al Dur IWPP Phase II project between 2019 and 2022.

The project was completed through effective integration of port handling, barging, roll-on/roll-off operations and specialised road transportation. It demonstrated Al Sharif’s capacity to execute large-scale power and water infrastructure logistics projects involving high cargo volumes, complex interfaces and demanding delivery requirements.

Need Reliable Transportation
Services?

Request a Transport Solution

Our team is ready to support your next project with efficient and dependable transport solutions.

Our Benefits

Why Choose Us?

.s0 { fill: #ee2a2a }
Features / Benefits

Modern Heavy Equipment

Advanced fleet designed for oversized and heavy cargo movement.

Features / Benefits

Safe & Reliable Operations

Strict safety procedures throughout transportation.

Features / Benefits

On-Time Delivery

Efficient scheduling and execution.

Features / Benefits

Experienced Team

Skilled operators and logistics professionals.

Features / Benefits

End-to-End Support

Planning, permits, transport, and coordination.

Features / Benefits

Customer Assistance

Dedicated support during every stage.